    Default wait for parallel job to complete

    Hi, In a job I am calling 3 jobs. two are running in parallel and third should wait until first and second jobs completes. but currently any of the jobs completes it will run the third job. I tried using wait for, dummy and success step but no luck. Please assist. Thanks

  2. #2
    Join Date
    Oct 2013
    Posts
    216

    Default

    You can put your two jobs into single job and then in main job you can put 3rd after this single job.
    -- NITIN --

  3. #3

    Default

    Thanks Nitin