We have two PDI carte servers Serv1 and Serv2. We can execute a mainjob on Serv1 that sends the execution of a subjob to Serv2 (the slave server).

The only return value we can get back to the master job on Serv1 is if the subjob was Success or Error.

We would also like to get a parameter value that was set in the subjob on Serv2. Is this somehow possible? The solution we have now is that we write the parameter to a database in the subjob and in the next step of mainjob read/set the parameter value from the database, but this seems rather not optimal solution.