    Hi all,

    I have multiple transformations to run. Some of them depends on the previous ones.

    Untill the previous one doesn't execute , the next one can not process.
    I want to put all such kind of transformations in a job.
    Then how the flow of the execution of transformations will be maintained?
    Is there any way so that I can specify the order of execution for transformations and jobs to maintain the hierarchy?

  2. #2
    Join Date
    May 2006
    Posts
    4,882

    Default

    You have to enter transformations 1 by 1 in jobs... in steps everything is executed in parallel... job entries run in sequence. So you should be ok.

    If you want to run transformations in parallel in a job you have to make multiple jobs and have them run un parallel by your scheduler.

    Regards,
    Sven

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •  
Privacy Policy | Legal Notices | Safe Harbor Privacy Policy

Copyright © 2005 - 2019 Hitachi Vantara Corporation. All Rights Reserved.