    If I've these steps:

    1)Table input1-> select values1 - > insert/update1

    2) Table input2-> select values2 - > insert/update2

    And I want insert this step in a single transformation: first 1) and then 2)
    How do I do?

    Thanks
    Mariarita



  2. #2
    Join Date
    Apr 2008
    Posts
    1,771

    Default

    If they can run at the same time, just add them to the same transformation.
    If 1. has to run before 2, then create a job and add those 2 transformations.
    Start -> transformation1 -> transformation2 -> success.

    Mick

  3. #3
    Join Date
    Apr 2009
    Posts
    337

    Default

    you can wait for a step to finish, if it is updating the same table (if that is what you mean by first 1) and then 2))
    Regards,
    Madhu

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •  
Privacy Policy | Legal Notices | Safe Harbor Privacy Policy

Copyright © 2005 - 2019 Hitachi Vantara Corporation. All Rights Reserved.